- Suppose That Your Firm Confronts The Following Project Choices Your Firm Will Limit Investment In The Coming Period To 1 (34.05 KiB) Viewed 69 times
Suppose that your firm confronts the following project choices. Your firm will limit investment in the coming period to
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Suppose that your firm confronts the following project choices. Your firm will limit investment in the coming period to
Suppose that your firm confronts the following project choices. Your firm will limit investment in the coming period to $64 million, and you have a required return of 7% for all 5 of these projects. NPV IRR Project Initial investment ($millions) ($millions) (%) Q $50 $16 16% R 14 7 22% S 31 11 14% T 8 1 12% U 12 4 21% If you want to maximize firm value subject to the constraint that investment cannot exceed $64 million, which project(s) should you undertake? Assume that none of these projects can be deferred to a subsequent year or rescaled. R, S, and U Q and S O R, S, T, and U O Q and R