QUESTION 1.1 A generating station has a maximum demand of 200MW, a load factor of 65% plant capacity factor of 50% and a

Posted: Sun May 15, 2022 4:46 pm
by answerhappygod
Question 1 1 A Generating Station Has A Maximum Demand Of 200mw A Load Factor Of 65 Plant Capacity Factor Of 50 And A 1
Question 1 1 A Generating Station Has A Maximum Demand Of 200mw A Load Factor Of 65 Plant Capacity Factor Of 50 And A 1 (165.02 KiB) Viewed 68 times
QUESTION 1.1 A generating station has a maximum demand of 200MW, a load factor of 65% plant capacity factor of 50% and a plant use factor of 75%. Determine: 1.1.1 The reserve capacity of the plant [5] 1.1.2 The daily energy produced [2] 1.1.3 Maximum energy that could be produced daily if the plant is fully loaded.[2] 1.1.4 The annual fixed charges if the annual fixed charges are R150.00 per kW of installed capacity. [2] 1.1.5 The cost per unit generated if the running charges are 8 cents per kWh. [4]