QUESTION 1.1 A generating station has a maximum demand of 200MW, a load factor of 65% plant capacity factor of 50% and a
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION 1.1 A generating station has a maximum demand of 200MW, a load factor of 65% plant capacity factor of 50% and a
QUESTION 1.1 A generating station has a maximum demand of 200MW, a load factor of 65% plant capacity factor of 50% and a plant use factor of 75%. Determine: 1.1.1 The reserve capacity of the plant [5] 1.1.2 The daily energy produced [2] 1.1.3 Maximum energy that could be produced daily if the plant is fully loaded.[2] 1.1.4 The annual fixed charges if the annual fixed charges are R150.00 per kW of installed capacity. [2] 1.1.5 The cost per unit generated if the running charges are 8 cents per kWh. [4]