QUESTION 1 Find the Critical Path for the following question. Place the CP at AN as follows: A,B,C,D,E,F,G,H, ect The circle must be filled in as follows: ES EF Activity Please do your own work ACTIVITY DURATION(DAYS) PREDECESSOR A 3 B 4. A C 3 B D 10 B
ACTIVITY DURATION(DAYS) PREDECESSOR A 3 B 4 A С 3 B D 10 B E 8 D F 4 D G 6 D H 8 C,E,F,G I 5 H j 5 H K 2 I L 6 J M 5 KAL 000