Activity A B С D E F G H Table G Immediate Predecessor EU (Weeks) 5 6 A 4 A 3 A 1 E 4. D&F 14 B&C 12 G&H 2 If you assume
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Activity A B С D E F G H Table G Immediate Predecessor EU (Weeks) 5 6 A 4 A 3 A 1 E 4. D&F 14 B&C 12 G&H 2 If you assume
Activity A B С D E F G H Table G Immediate Predecessor EU (Weeks) 5 6 A 4 A 3 A 1 E 4. D&F 14 B&C 12 G&H 2 If you assume that the expected duration of the project in Table G is 26 weeks and the standard deviation of the critical path is 205 weeks, what is the latest date to start this project to have at least a 95% chance of completion by December 24, 2022, assuming that work is done every week from start to finish? Select one 2 December 1 November 24 Vovember 30 O November 27