A project task has an early start time of 4, a late start time of 6, an early finish time of 9, and a late finish time o

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A project task has an early start time of 4, a late start time of 6, an early finish time of 9, and a late finish time o

Post by answerhappygod »

A project task has an early start time of 4, a late start time
of 6, an early finish time of 9, and a late finish time of 11. What
is the task’s slack?
A. 4
B. 2
C. 9
D. 3
E. 0
F. 6