There are five
activities on a project’s critical path and they have standard
deviations of 3, 4, 4, 6, 6 days. The standard deviation (in
days) of the critical path is:
7.8
9.8
10.6
4.6
10.2
8.8
There are five activities on a project’s critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The stan
-