There are five activities on a project’s critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The stan

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

There are five activities on a project’s critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The stan

Post by answerhappygod »

There are five
activities on a project’s critical path and they have standard
deviations of 3, 4, 4, 6, 6 days. The standard deviation (in
days) of the critical path is:
7.8
9.8
10.6
4.6
10.2
8.8
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply