Use the activity-on-arrow diagram below to answer the following two questions. E (4) G (4) A (4) C (3) |(3) B (3) F (4) H (2) D (3) What is the project completion time? A. 15 days - What is the slack for task E? B. 16 days C. 17 days D. 18 days E. 19 days F. zero days G. one day H.two days
1. three days J. four days