Page 1 of 1

The following bids were received on a project. Using a simple bid analysis to answer the following questions. Contractor

Posted: Thu May 05, 2022 12:06 pm
by answerhappygod
The Following Bids Were Received On A Project Using A Simple Bid Analysis To Answer The Following Questions Contractor 1
The Following Bids Were Received On A Project Using A Simple Bid Analysis To Answer The Following Questions Contractor 1 (18.08 KiB) Viewed 39 times
The following bids were received on a project. Using a simple bid analysis to answer the following questions. Contractor A $4.723.400.00 Contractor B $4.758,570.00 Contractor C $4,741,750.00 Contractor D $4.705,875.00 Contractor E $4,779,320.00 What is the smallest variance between bids? What is the largest variance between bids? What is the total range? Which Contractor would you recommend and give reasons for the selection?