The following bids were received on a project. Using a simple bid analysis to answer the following questions. Contractor
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The following bids were received on a project. Using a simple bid analysis to answer the following questions. Contractor
The following bids were received on a project. Using a simple bid analysis to answer the following questions. Contractor A $4.723.400.00 Contractor B $4.758,570.00 Contractor C $4,741,750.00 Contractor D $4.705,875.00 Contractor E $4,779,320.00 What is the smallest variance between bids? What is the largest variance between bids? What is the total range? Which Contractor would you recommend and give reasons for the selection?