Project Z has a current budget of $20 million. The project is
working on a 20-month schedule. After month 6, the following
performance data is available: Actual Cost (AC) = $6.5 million;
Planned Value (PV) = $6.8 million; Earned Value = $7.1 million.
What would be the Estimate at Completion, assuming that current
cost performance will continue for the rest of the project?