Consider this Work Breakdown Structure ... Immediate Duration Activity Predecessor(s) (Weeks) A none 11 A C A D C E B, D
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Consider this Work Breakdown Structure ... Immediate Duration Activity Predecessor(s) (Weeks) A none 11 A C A D C E B, D
Consider this Work Breakdown Structure ... Immediate Duration Activity Predecessor(s) (Weeks) A none 11 A C A D C E B, D 13 F D 16 G E, F 12 At a minimum, how long will this project take (in weeke B 19 17 11