3. The following table shows information related to the major activities of certain project. Activity Immediate Predeces
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
3. The following table shows information related to the major activities of certain project. Activity Immediate Predeces
3. The following table shows information related to the major activities of certain project. Activity Immediate Predecessor (4 points) Optimistic Time (Week) Most Likely Time Pessimistic Time A (Week) (Week) 6 B 10 14 ---- 5 C 08 12 A 9 12 15 D B 6 6 6 E C 7 7 7 F E 10 14 20 G D 11 16 22 H E, F 10 15 20 1 G,H 20 20 20 a. Draw the project network b. Determine the expected activity times for all activities c. Determine variances of the activity times for all critical activities 10 A (