Job 731 was recently completed. The following data have been recorded on its job cost sheet: Direct material $15 per yard Direct labor $20 per hour Direct material used 175 yards Direct labor hours 75 hours Machine hours 120 hours The predetermined overhead rate is 65% of direct labor costs. What is the total cost for Job 731?