5. A tower was erected in 7,000 hours. The company feels that the learning rate per tower will be 0.80 on doubled units.
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
5. A tower was erected in 7,000 hours. The company feels that the learning rate per tower will be 0.80 on doubled units.
5. A tower was erected in 7,000 hours. The company feels that the learning rate per tower will be 0.80 on doubled units. How many towers will have to be erected before the time per tower is reduced to 3,000 hours? How much time will be consumed on the fiftieth tower?
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!