6. Use Rational Method to size each pipe in the network for the 25-yr peak discharge. (Size each pipe assuming full flow
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
6. Use Rational Method to size each pipe in the network for the 25-yr peak discharge. (Size each pipe assuming full flow
6. Use Rational Method to size each pipe in the network for the 25-yr peak discharge. (Size each pipe assuming full flow). Assume concrete pipes with n=0.013 Basin Area tc PIPE LENGTH Slope A [ac] [min] [ft] [%] A 7 0.6 25 1 500 1.2 B 5 0.8 15 2 500 1.0 с 8.5 0.6 30 3 500 1.2 B D PIPE3 D 6 0.8 20 4 500 0.9 10 15 20 30 60 Duration 5 [min] Intensity 8.4 7.02 5.96 5.26 4.42 2.97 [in/hr]