The following data are cross-section notes of the ground which will be excavated for a roadway having a base width of te
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The following data are cross-section notes of the ground which will be excavated for a roadway having a base width of te
The following data are cross-section notes of the ground which will be excavated for a roadway having a base width of ten meters: Station Station 116 154 10+ 10+ 3.0 2.1 2.1 2.6 2.75 3.4 6.1 0 5.3 5.9 0 7.1 Determine the volume of excavation by end-area method (in m³)