Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the
Posted: Wed May 04, 2022 8:43 am
Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the number of trucks at the highest production rate. - Shovel has a 3-cy bucket - Shovel cycle time is 20 sec. Bucket fill factor is 0.95 -Job efficiency is 50-min per hour and job condition is average - Rear-dump truck capacity is 20 LCY (truck fill factor: 110%) Haul distance is 3 mi. - Haul speed is 16 mph and return speed is 22 mph.