Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the

Posted: Wed May 04, 2022 8:43 am
by answerhappygod
Problem Given The Following Information On A Shovel Truck Operation Identify The Number Of Bucket Loads As Well As The 1
Problem Given The Following Information On A Shovel Truck Operation Identify The Number Of Bucket Loads As Well As The 1 (28.19 KiB) Viewed 22 times
Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the number of trucks at the highest production rate. - Shovel has a 3-cy bucket - Shovel cycle time is 20 sec. Bucket fill factor is 0.95 -Job efficiency is 50-min per hour and job condition is average - Rear-dump truck capacity is 20 LCY (truck fill factor: 110%) Haul distance is 3 mi. - Haul speed is 16 mph and return speed is 22 mph.