Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the
Problem) Given the following information on a shovel/truck operation, identify the number of bucket loads as well as the number of trucks at the highest production rate. - Shovel has a 3-cy bucket - Shovel cycle time is 20 sec. Bucket fill factor is 0.95 -Job efficiency is 50-min per hour and job condition is average - Rear-dump truck capacity is 20 LCY (truck fill factor: 110%) Haul distance is 3 mi. - Haul speed is 16 mph and return speed is 22 mph.