Activity ID Name 1 2 BD2 3 BD3 4 5 BD5 6 BD6 7 BD7 8 BD8 9 10 BD10 11 BD11 12 BD12 13 BD13 14 BD14 BD15 15 16 17 BD17 18 BD18 Project: cee340_BD housing Date: Sun 4/10/22 ID Duration BD HOUSING PROJECT 32 days Notice to Proceed 0 days Project completion Pre construction Submittals Approve submittals 0 days 14 days 7 days 5 days Fabrication and Delivery 10 days Site Prep 2 days Construction 25 days Excavation 4 days. 3 days 6 days 10 days 5 days 3 days 7 days 5 days Pour concrete Foundation Walls Exterior finishes Landscape Project closeout Final clean Punch list 2 days Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary BD HOUSING PROJECT SCHEDULE Finish Predecessors Wed 10/13/21 Mon 8/30/21 Wed 10/13/21 18 Total Slack 0 days 11 days. 0 days 11 days 2 11 days 5 11 days. 13 days 7,6 11 days Fri 9/17/21 Wed 9/8/21 Wed 9/15/21 Mon 9/13/21 Fri 9/17/21 Mon 10/4/21 Thu 9/23/21 Tue 9/28/21 Wed 9/8/21 Wed 9/22/21 Wed 9/29/21 0 days 8 11 days 10 11 days. 0 days 12 0 days 13 0 days 14 0 days Mon 10/4/21 Wed 10/13/21 0 days Mon 10/11/21 15,14 0 days Wed 10/13/21 17 0 days Manual Task Duration-only Manual Summary Rollup Manual Summary C Start-only Finish-only External Tasks External Milestone Start Mon 8/30/21 Mon 8/30/21 Wed 10/13/21 Mon 8/30/21 Mon 8/30/21 Thu 9/9/21 Mon 8/30/21 Thu 9/16/21 Mon 8/30/21 Mon 9/20/21 Fri 9/24/21 Mon 8/30/21 Thu 9/9/21 Thu 9/23/21 Thu 9/30/21 Tue 10/5/21 Tue 10/5/21 Tue 10/12/21 ] Type September 2021 October 2021 21 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 ◆8/30 ► 10/13 Fixed Duration Fixed Units Fixed Units Fixed Duration Fixed Units Fixed Units Fixed Units Fixed Units Fixed Duration Fixed Units Fixed Units Fixed Units Fixed Units Fixed Units Fixed Units Fixed Duration Fixed Units Fixed Units Deadline Critical Critical Split Progress Manual Progress Slack ↓
Refer the BD Housing project output file and answer Q. No. 1 to 5. 1. Write down the activity IDs and names of the activities which will not be delayed if this project is delayed by 10 days. Write down the reasons why these activities will not be delayed. Use the following table format to answer the questions (10 Points) Name of the activities Reasons Activities ID
Activity ID Name 1 2 BD2 3 BD3 4 5 BD5 6 BD6 7 BD7 8 BD8 9 10 BD10 11 BD11 12 BD12 13 BD13 14 BD14 BD15 15 16 17 BD17 18
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Activity ID Name 1 2 BD2 3 BD3 4 5 BD5 6 BD6 7 BD7 8 BD8 9 10 BD10 11 BD11 12 BD12 13 BD13 14 BD14 BD15 15 16 17 BD17 18
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!