draw an activity-on node network diagram for the following project, including the estimated time for each activity. d) w
Posted: Wed May 04, 2022 8:14 am
draw an activity-on node network diagram for the following
project, including the estimated time for each activity.
d) what are the chances that you can finish this project in 34
days?
e) if I gave you an extra resources (say 5 person-weeks of work)
what would you do with them?
Activity A B D E F H Optimistic Time(weeks) Time (weeks) Time (weeks) 2 3 4 5 12 4 6 8 11 3 7 1 9 4 2 Most likely Pessimistic Predecessor A, B 1 7 9 2 11 8 6 4 14 3 13 12 16 10 C C F C G, H I