Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

draw an activity-on node network diagram for the following project, including the estimated time for each activity. d) w

Post by answerhappygod »

draw an activity-on node network diagram for the following
project, including the estimated time for each activity.
Draw An Activity On Node Network Diagram For The Following Project Including The Estimated Time For Each Activity D W 1
Draw An Activity On Node Network Diagram For The Following Project Including The Estimated Time For Each Activity D W 1 (125.14 KiB) Viewed 35 times
d) what are the chances that you can finish this project in 34
days?
e) if I gave you an extra resources (say 5 person-weeks of work)
what would you do with them?
Activity A B D E F H Optimistic Time(weeks) Time (weeks) Time (weeks) 2 3 4 5 12 4 6 8 11 3 7 1 9 4 2 Most likely Pessimistic Predecessor A, B 1 7 9 2 11 8 6 4 14 3 13 12 16 10 C C F C G, H I