b. Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A res
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
b. Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A res
b. Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A response of "O" is equivalent to being not applicable.) Item: Driveshaft subassembly Lot Size: L4L Lead Time: 3weeks Week 2 3 5 6 8 Gross 20 15 30 30 60 requirements Scheduled receipts Projected on-hand inventory Planned receipts 10 1 40 85 4 25 ロロ ロロ ロロ ロロ 7 60 ロロ ロロ ロロ