Which of the following criteria on test progress would enable the business to determine a likely go live date? (i) Numbe

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Which of the following criteria on test progress would enable the business to determine a likely go live date? (i) Numbe

Post by answerhappygod »

Which of the following criteria on test progress would enable the business to determine a likely go live date?
(i) Number of tests planned versus number of tests executed
(ii) Number of high priority defects outstanding
(iii) The test teams timesheets in order to show how much effort has been devoted to testing
(iv) Number of tests passed and number failed
(v) Number of defects found in each development area
(vi) The rate at which defects are being found

A. (ii), (iii), (iv)
B. (i), (iii), (v)
C. (i), (ii), (vi)
D. (iv), (v), (vi)
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply