You are the business analyst for your organization. Management realizes that a proposed solution has risks that may cause the entire project to fail. They would like you to prioritize the requirements with maximum risks first so that if the project fails, there is little loss of capital in the project implementation.
What requirements prioritization approach is management asking you to create in this instance?
A. Implementation difficulty
B. Business or technical risk
C. Likelihood of success
D. Relationship to other requirements