You are a project manager in an organization that uses Project Server 2013. You have access to Project Web App (PWA) but no access to Project Professional 2013 for making changes to your schedule.In your organization, projects begin work after the project sponsor provides funding for the first phase of the project.You need to take a snapshot of your schedule and make that information available to theProject Management Office (PMO), who will view it in PWA.What should you do?
A. Set all tasks to auto scheduled and publish the project.
B. Set the baseline and publish the project.
C. Clear the baseline and publish the project.
D. Change to the Tasks Tracking view and publish the project.
You are a project manager in an organization that uses Project Server 2013. You have access to Project Web App (PWA) but
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
You are a project manager in an organization that uses Project Server 2013. You have access to Project Web App (PWA) but
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!