You are a project manager for an organization that uses Project Server 2013.You are evaluating resource information in t

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You are a project manager for an organization that uses Project Server 2013.You are evaluating resource information in t

Post by answerhappygod »

You are a project manager for an organization that uses Project Server 2013.You are evaluating resource information in the Resource Center. The following information is presented to you on the Resource Availability page:You need to determine if a team member has available capacity to assist on another project or if this team member is overallocated.What should you do?
You Are A Proje 1
You Are A Proje 1 (16.33 KiB) Viewed 92 times
A. The team member has 32 hours available for enterprise projects and should be assigned to the other project.
B. The team member has 8 hours available for enterprise projects and should be assigned to the other project.
C. The team member is overallocated by 32 hours on enterprise projects and is not available to assist on the other project. You should perform resource leveling.
D. The team member is overallocated by 8 hours on enterprise projects and is not available to assist on the other project. You should perform resource leveling.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply