Your organization uses Project Professional 2013.You are setting up a preliminary schedule by using manually scheduled t

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Your organization uses Project Professional 2013.You are setting up a preliminary schedule by using manually scheduled t

Post by answerhappygod »

Your organization uses Project Professional 2013.You are setting up a preliminary schedule by using manually scheduled tasks.As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task.You need to determine the cause of the wavy red line.What should you do?

A. Evaluate the task to determine if there is a deadline.
B. Insert the Constraint Type field and view the task constraints.
C. Evaluate the task by using the Task Inspector.
D. View the Resource Sheet to see if you have overallocated resources.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply