You are a project manager who uses Project Professional 2013.A senior stakeholder asks you to update your project to ref

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You are a project manager who uses Project Professional 2013.A senior stakeholder asks you to update your project to ref

Post by answerhappygod »

You are a project manager who uses Project Professional 2013.A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure.You need to reflect the closure within your schedule.What should you do?

A. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.
B. Open the Project Calendar and modify the default work week by setting the dates as non-working time.
C. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.
D. Open the Project Calendar and enter the planned closure in the Exceptions tab.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply