Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is more than$125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric's relationship withthe vendor. What positive risk response has happened in this instance?
A. Transference
B. Exploiting
C. Sharing
D. Enhancing
Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable dis
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable dis
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!