You work as the project manager for Company Inc. The project on which you are working has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?
A. Resource Management Plan
B. Communications Management Plan
C. Risk Management Plan
D. Stakeholder management strategy