All of the following statements about Risk Communications are true, EXCEPT:
A. The Stakeholders should be continuously informed about risks, including the potential impact of these risks and the plans for responding to each risk.
B. The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner during Daily Standup Meetings.
C. The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to the Scrum Team.
D. Information related to risks is maintained and updated through the Risk Burndown Chart.