Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A compacted fill must be placed under all spread footings that have a minimum of 98% relative compaction of the MDD. The

Post by answerhappygod »

A compacted fill must be placed under all spread footings that
have a minimum of 98% relative compaction of the MDD. The max
dry density is 122.6 pcf. The wet density of 140,8 pcf has a water
content of 21.5% Has the contractor met the required degree for
relative compaction?