Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Me
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Me
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 32 and a Path Standard Deviation 5. For Path 1-3-4-5 we have a Path Mean = 35 and a Path Standard Deviation = 3. Determine both the Probability that Path 1-2-5 will finish in 35 Days or Less and the Probability that the Project will finish in 35 Days or Less. 0.84134474 : 0.628911531 0.725746935:0.362873467 0.788144666: 0.496971394 0.884930268:0.744531427