An automobile detailing shop has the following jobs waiting to be processed. All jobs (cars requiring detailing) must first be cleaned, then waxed. Job J1 J2 33 34 35 Cleaning Time 75|1108 Waxing Time 2 4 5 9 6 a. What processing sequence will minimize the makespan for these jobs? b. What is the minimum makespan for this set of five jobs?