If 10 workers, working for 4 hours complete the work in 12 days, in how many days will 8 workers working for 6 hours com
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
If 10 workers, working for 4 hours complete the work in 12 days, in how many days will 8 workers working for 6 hours com
If 10 workers, working for 4 hours complete the work in 12 days, in how many days will 8 workers working for 6 hours complete the same work? a 50 b 10 c 25 d 5