Determine the project duration What is the earliest possible time activity G can start? What is the earliest possible time activity H can finish? What is the Free Float for activity A? What is the latest possible time activity B can start? What is the latest possible time activity C can finish? What is the Total Float for activity A?
For the network and activities duration shown below; answer the following questions B SF+4 E H FF A SS+3 с SF F SS FS+4 D FF+1 G Activity Duration (days) А 5 B 13 C 6 D 3 E 12 F 26 G 4 H 2
Determine the project duration What is the earliest possible time activity G can start? What is the earliest possible ti
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Determine the project duration What is the earliest possible time activity G can start? What is the earliest possible ti
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!