the owner/ operator of the local franchise of handy man inc. has
four jobs to do today, shown in order that they recieve
if he uses the earliest due date first? EDD priority rule to
schedule these jobs, what will be the average job lateness?
a. 0 hours
b. 2.25 hours
c. 1.75 hours
d, 1.5 hours
e. 2 hours