PROJECT MANAGEMENT - Q1. (10 points) Consider the following project. Activity AB = ت امها ت ادب د > Immediate Activity Time Processor (days) 8 6 4 B 5 с 7 CD 7 D 9 E,F,G 6 H a) Determine the critical path. b) Determine the estimated completion time of the project. c) Determine the slack for activity D. d) Determine the slack for activity F. c) How much can activity F be delayed without delaying the project completion?