A project manager wants to compress her project schedule (week).
She should compress one time unit (week) per move to reduce the
project schedule until she reach the has crashed point of the
network.
The total indirect cost for the project is $2,000 and there is a
savings of $100 per time unit reduced.
Answer following questions regarding the project time reduction
by 2 weeks (from 20 weeks to 18 weeks).
Question 7 (6 points)
What is the project total cost (direct + indirect) when she has
reduced the project duration from 20 to 19 weeks?
Question 7 options:
8,950
$8,340
$8,400
$9,140
$8,750
Which activity should be selected to reduce project duration
from 20 weeks to 19 weeks?
Question 8 options:
1. b
2. E
3. A
4. D
5. C
A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to re
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to re
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!