Consider the time-phased work packages (cost in $1,000) and
network diagram for the project baseline budget.
Develop the project scheduled budget to answer the following
questions.
Question 5 (5 points)
What is the project required budget in month 8?
Question 5 options:
12,500
21,000
19,000
28,000
15,000
Question 6 (5 points)
What is the project required budget in month 11?
Question 6 options:
18,000
4,000
25,000
12,000
9,000
Consider the time-phased work packages (cost in $1,000) and network diagram for the project baseline budget. Develop the
-