The following data have been collected for a management information system project. Task 15 19 o o 154 19 А 2 8 15 11 23 A E I Weekly Cost 22 11 B | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 5 C 557 832 DS 555 E 10 10 10 10 F 10 10 10 10 55 G5555 H 10 10 5 5 11 15 0 11 4 15 0 0 o UR 5 6 11 194 23 5 5 D 17 F 22 11 8 19 11 Period 6 Earned Value Management Table Task % Complete EV AC PV A A Finish 10 B 25% 15 C 33% 12 D 0% 0 Cumulative Totals 37 Period 8 Task EV AC PV % Complete Finish А 10 B 30% 20 с 60% 25 D 0% 0
The project's PV at the end of period 6 is .......... O 14 36 35 32 23
The project's EAC at the end of period 6 is ........... *Assume the future work will be accomplished to cover the performance gap. It means the CPI will not be the same* 369 148 314 298 257
The project's EAC at the end of period 6 is *Assume the future work will be accomplished to cover the performance gap. It means the CPI will not be the same* 369 148 314 298 257
The project's SPI at the end of period 8 is 1.47 0.69 1.96 0.25 0.36
The project's EV at the end of period 6 is HERS 45 30 21 28 11
The following data have been collected for a management information system project. Task 15 19 o o 154 19 А 2 8 15 11 23
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The following data have been collected for a management information system project. Task 15 19 o o 154 19 А 2 8 15 11 23
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!