Network Diagram With Lag Consider the below project network diagram with lags. Lag 3 Task 2 Task 1 3 к 7 Lag 5 А | | в x Task 5 G 2. C D Task 6 F E Task 8 w Task 3 3 H 00 Lag 3 G 2 N Lag 4 Lag 2 Task 4 Y Lag 4 Z Task 7 1 J 2 Answer the following questions regarding Early Start, Early Finish, Late Start, Late Finish, and Slack values.
What is the value of "C"? 011 15 13 0 14 18
What is the value of "A"? 07 011 010 O 9 08
What is the value of "E"? 021 019 0 31 26 028