Q1. (10 points) Consider the following project. Activity A B с D E F G H Immediate Activity Time Processor (days) 8 6 AB
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Q1. (10 points) Consider the following project. Activity A B с D E F G H Immediate Activity Time Processor (days) 8 6 AB
Q1. (10 points) Consider the following project. Activity A B с D E F G H Immediate Activity Time Processor (days) 8 6 AB 4 B 5 C 7 CD 7 D 9 EFG 6 a) Determine the critical path. b) Determine the estimated completion time of the project. c) Determine the slack for activity D. d) Determine the slack for activity F. c) How much can activity F be delayed without delaying the project completion?