A company must perform a project consisting of seven activities. The time estimates and predecessors of the activities a

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A company must perform a project consisting of seven activities. The time estimates and predecessors of the activities a

Post by answerhappygod »

A company must perform a project consisting of seven activities.
The time estimates and predecessors of the activities are: (1)
Activity A without immediate predecessor, which last 3 day, (2)
Activity B with activity A as immediate predecessor, which last 3
days, (3) Activity C with activity A as predecessor, which last 3
day, (4) Activity D with activity B as predecessor, which last 1
days, (5) Activity E with activity C as predecessor, which last 2
days, (6) Activity F with activities D and E as predecessors, and
last 1 day, and (5) Activity G with activity F as predecessor,
which last 2 days. Which activities have slack in this project?
A and B
C and E
B and D
D and F
E and F