2. A road construction project consists of 14 sections. The objective chart and program chart are given. Assume that eac
2. A road construction project consists of 14 sections. The objective chart and program chart are given. Assume that each month consists of 20 working days on average. Please calculate and draw the LOB representing the beginning of month 9. 15 14 13 12 11 10 TI 8 Sections ONWAU O INW 2 LLLLL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Months 7 5 4 Control points 3 1 1 6 1 1 2 1 Rough Grade Finish Grade Agg. Base 5 Concrete 9 Concrete Curbs 25 20 15 7 8 5 1 80 Lead time in working 1 55 1 35 1 20 1 13 1 5 1 0 days