QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time(secs) Immediate Predecessor 34 none b 20 a a b c d 10 b 16 b e C f 10 24 d, e g 38 f Without considering forecasted demand, what is the minimum possible cycle time for this production line? Assume you can hire only one person for each task. bo 38 seconds 152 seconds O 10 seconds 34 seconds 20 seconds