H&B Inc. uses a standard cost system and calculates their application rates using direct labour hours. The budgeted proddiction for the year is 17,000 units. This year the company had the following standards: Standard direct labour hours per unit: 2 hours Variable overhead application rate: $5 per direct labour hour Fixed overhead application rate: $7 per direct labour hour The company also had the following actuals: Production: 17,000 units Variable overhead: $195,840 Fixed overhead: $271,320 Total direct labour hours: 40,800 What is the fixed overhead spending variance?
What is the fixed overhead spending variance? a) $33,320 favourable Ob) $14,280 favourable c) $14,280 unfavourable d) $33,320 unfavourable
H&B Inc. uses a standard cost system and calculates their application rates using direct labour hours. The budgeted prod
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
H&B Inc. uses a standard cost system and calculates their application rates using direct labour hours. The budgeted prod
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!