8.2 Make a clear and neat sketch of the network specified below using precedence notation. On the precedence diagram cal
8.2 Make a clear and neat sketch of the network specified below using precedence notation. On the precedence diagram calculate and show the early start (EST), early finish (EFT), late start (LST), late finish (LFT), and TF in each activity. Start calculations with day zero. Show the critical paths with colored pencil . Label Duration Must Follow Operations A 2 B 4 А 7 A D 3 A E 5 A 7 B G 6 B H 7 F 5 G 3 K 8 O,G L 9 HI M 4 N 7 FJK DK E,K 8 P 6 Q 10 MN NO 2,0,P Q,R R 5 S 7