Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

A contractor suggests using shaft wall material instead of the specified block for the elevator shafts because he is mor

Post by answerhappygod »

A contractor suggests using shaft wall material instead of the
specified block for the elevator shafts because he is more familiar
with it and can install it faster. Assuming the system still
meets all codes and functionality of the building, if the
contractor provides a 10,000 dollar credit this would be an example
of value engineering?
True
False